Time
and work
This chapter based on
relationship between time and work. As it is very clear to all of us that the
work is directly related with time. As one can say if a particular person or
machine works for more time then more work will be done and if it devoted less time
then it yields less work i.e., output of a machine or person is directly
proportional to time, provided the he/she maintained his/her efficiency during
the work.
Concept
of Efficiency
Suppose a person can
complete a particular work in 2 days then we can say that each day he does half
of the work or 50% work each day. This is clear that his efficiency is 50% per
day.
Now, if a person can
complete a work in n days then his one day’s work = 1/n
And this one day’s work
in terms of percentage is called his efficiency.
Also if a person can
complete 1/n work in one day, then he can complete the whole work in n days.
Relation
between work of 1 unit of time and percentage efficiency.
A person can complete
his work in n days, then his one days work = 1/n, his percentage efficiency =
1/nx100
All problems of this
chapter can be solved through two methods:
1 1) Unitary method
2 2)
Percentage efficiency
Problems:
1. 1) A can do a job in 12 days and B can do
the same job in 6 days, in how many days working together they can complete the
job?
Solution:
A’s
1 days work = 1/12
B’s
1 days work = 1/6
Therefore
(A+B)’s 1 day works = 1/12 +1/6 = 3/2 =1/4
Time
taken by both to finish the whole work = 1/1/4 = 4 days
Alternatively:
Efficiency of A = 100/12 = 8.33%
Efficiency
of B = 100/6 = 16.66%
Both
A+B = 25%
Time
taken by both to finish the whole work = 100/25 = 4 days
2. 2) A can do a job in 10 days, B can do the
same job in 12 days and C can do the same job in 15 days. In how many days they
will finish the work together?
Solution:
A’s
1 days work = 1/10
B’s
1 days work = 1/12
C’s
1 days work = 1/15
(A+B+C)’s
1 days work = 1/10+1/12+1/15 = 15/60 = ¼
Since
they can complete 1/4work in 1 day. So they will finish the whole work in 1/1/4
= 4 days
Alternatively:
A’
efficiency = 10%
B’s
efficiency = 8.33%
C’s
efficiency = 6.66%
Combined
A,B and C = 10+8.33+6.66 = 25%
Hence they will take 100/25 = 4 days